Karnataka State Highways Improvement Project - I (KSHIP-I)

Road Works taken up and completed under World Bank Assistance

Package No Description of Road Contractor Name(M/s) Length (in kms) Contract Period
(in months)
Contract Amount (Rs.in Cr.) Expenditure.
( Rs.in Cr.)
Starting date as per contract Completion date as per Contract Actual date of completion Status
U1 Upgradation of road from Kalmala-Junction to Sindhanur NCC - Maytas(JV),Hyderabad 76.70 30.00 68.00 94.75 Jan-02 Jul-04 Mar-06 Completed
U2 Upgradation of road from Sindhanur to Budugumpa KMC Constructions Limited,Hyderabad 77.54 30.00 72.00 87.61 Jan-02 Jul-04 Sep-05 Completed
U3 Upgradation of road from Hattigudur to Bidar HCC - SEL (JV),Mumbai 188.43 48.00 140.00 174.00 Jan-02 Jan-06 Jul-06 Completed
U4 Upgradation of road from Bijapur to Tikota Bharat - PCC (JV), Sholapur 20.15 17.00 15.00 14.00 Feb-02 Dec-04 May-04 Completed
U5 Upgradation of road from AP Border to Kalmala Junction Maytas Infra Ltd. Hyderabad 31.00 24.00 29.00 36.00 Jan-02 Jan-04 Jul-05 Completed
U6 Upgradation of road from Sankeshwar to Yaragatti Tarmat Infrastructural & Engineering Ltd.,Mumbai 73.18 34.00 77.24 93.00 Mar-03 Mar-06 Aug-09 Completed
U7A Upgradation of road from Bijapur to Krishna Bridge PBA Infrastructure Ltd., Mumbai 48.10 30.00 51.11 59.45 May-04 Nov-06 Sep-07 Completed
U7B Upgradation of road from Krishna Bridge to Lokapur Patel – KNR (JV), Hyderabad 55.64 30.00 67.62 77.71 May-04 Nov-06 Jun-07 Completed
U8 Upgradation of road from Hungund to Belgaum KMC Constructions Co. Ltd. 170.31 36.00 281.00 348.15 Mar-03 Mar-06 Dec-06 Completed
U11 Upgradation of road from Hiriyur to Bellary L&T Ltd., Chennai 144.00 36.00 269.00 277.85 Mar-03 Mar-06 Jul-06 Completed
BR-1 Reconstruction of 9 Bridges SP.Lakshmanan,Chennai - 12.00 2.45 2.08 Nov-01 Nov-02 Nov-02 Completed
U3-BR Construction of PSC Bridge across Bennethora River BVSR Constructions Pvt Ltd., Hyderabad - 17.00 7.79 2.79 Dec-05 May-07 - Terminated & handed over to NH
U4-BR Construction of Bridge at Ch.12.334 of road road from Bijapur to Tikota B.V.Subba Reddy, Hyderabad - 12.00 2.56 2.94 Jun-05 Jun-06 Aug-08 Completed
BP1 Construction of Bypass for Raichur Town in Raichur District(Contrcat No.BP1) Reddy Veeranna Constructions Pvt Ltd., Bangalore 8.00 15.00 15.62 15.62 Jan-06 Apr-07 Jan-14 Completed
BP2 Construction of Bypass for Bijapur for Bijapur Town Mehul Constructions Co.Pvt.Ltd., Solapur 7.00 12.00 9.81 13.75 Dec-06 Dec-07 Nov-08 Completed
M1 Rehabilitation of road from Mudgal to Hungund HP Madhukar,Hubli 39.68 15.00 12.20 17.57 Jul-03 Oct-04 Apr-06 Completed
M2 Rehabilitation of road from Tikota to Badachi Rohan Builders (India) Pvt Ltd. – J. M Mhatre (JV) 42.80 16.00 10.00 9.43 Feb-02 Jun-03 Aug-04 Completed
M3 Rehabilitation of road from Athani to Shedbal Tarmat Infrastructural & Engineering Ltd.,Mumbai 49.51 14.00 13.00 11.69 Feb-02 Apr-03 Mar-04 Completed
M4 Rehabilitation of road from Shedbal to Sankeshwar SP Lakshamanan ,Chennai 55.50 22.00 12.29 17.03 Feb-02 Sep-04 May-06 Completed
M5 Rehabilitation of road from Srirangapatna to Chinya Maheshwar Naidu,Hyderabad 32.00 11.00 16.95 20.42 Jun-05 May-06 Dec-06 Completed
M6 Rehabilitation of road from Chinya to Nelligere Maheshwar Naidu,Hyderabad 33.00 11.00 16.03 21.80 Nov-05 Oct-06 Jul-07 Completed
M7 Rehabilitation of road from Nelligere to Kibbanahalli KMC Constructions Co. Ltd. 47.00 14.00 21.29 25.65 Nov-05 Jan-07 Jun-07 Completed
M8 Rehabilitation of road from Kibbanahalli to Huliyar M/s National Asphalt Products and Construction Company 36.46 14.00 11.98 13.03 Nov-01 Jan-03 Mar-03 Completed
M9 Rehabilitation of road from Huliyar to Hiriyur KNR Constructions Hyderabad 48.65 17.00 27.00 25.13 Dec-04 May-06 Mar-07 Completed
M10 Rehabilitation of road from Bellary to Devinagar Rani Constructions Pvt. Ltd 40.00 15.00 20.00 21.32 Jul-03 Oct-04 Nov-06 Completed
M11 Rehabilitation of road from Devinagar to Sindhanur R.N. Shetty & Co.Hubli 42.72 15.00 20.55 30.18 Jun-05 Sep-06 Oct-07 Completed
M12 Rehabilitation of road from Sindhanur to Lingsugur R.N. Shetty & Co.Hubli 51.96 20.00 11.37 13.44 Jan-02 Oct-03 Jun-04 Completed
M13 Rehabilitation of road from Lingsugur to Hattigudur Tantia Construction Company Limited 67.44 22.00 15.87 20.36 Jan-02 Dec-03 Oct-05 Completed
M14 Rehabilitation of road from Mariyammanahalli to Ittagi R.N. Shetty & Co.,Hubli 52.95 20.00 31.48 30.32 Nov-04 Jul-06 May-07 Completed
M15 Rehabilitation of road from Ittagi(Kallaubavale cross) to Harihara Afcon Infrastructure LTd.,Mumbai 53.93 20.00 31.00 34.28 Dec-04 Aug-06 May-08 Completed
M16 Rehabilitation of road from Harihara to Honnali Reddy Veeranna Constructions Pvt.Ltd 35.37 15.00 21.75 23.21 Dec-04 Mar-06 Apr-07 Completed
M17 Rehabilitation of road from Honnali to Shimoga M. Venkata Rao, Vishakapatnam 41.22 23.00 11.48 17.38 Nov-01 Dec-02 Oct-03 Completed
M18 Rehabilitation of road from Belur to Chikkamagalur M/s Maytas Infra Limited,Hyderabad 24.00 23.50 8.17 9.63 Nov-01 Jun-02 Nov-03 Completed
M19 Rehabilitation of road from Chikkamagalur to Tarikere M/s Larsen & Toubro 57.70 18.00 14.95 25.25 Jan-01 May-04 Oct-04 Completed
M24 Rehabilitation of road from Alnawar to Yellapur Patel Engineering Ltd., Hyderabad 57.10 21.00 24.40 26.65 Feb-04 Feb-06 Dec-06 Completed
M25 Rehabilitation of road from Yellapura to Sirsi M. Venkata Rao, Vishakapatnam 51.00 18.00 21.12 21.12 Jun-05 Dec-06 May-09 Completed
M26 Rehabilitation of road from Sirsi to Mavingundi M. Venkata Rao, Vishakapatnam 53.00 9.00 20.02 20.02 Dec-05 Sep-06 May-09 Completed
M27 Rehabilitation of road from Kumbarvada to Sadashivgarh M. Venkata Rao, Vishakapatnam 64.00 24.00 19.31 21.00 Mar-05 Mar-07 Apr-07 Completed
M28 Rehabilitation of road from Ramanagara(Londa) to Kumvbarvada B. Seenaiah & Co., Hyderabad 56.85 21.00 15.90 17.43 Jun-04 Feb-06 Mar-07 Completed
M29 Rehabilitation of road from Yaragatti to Hulikatti KNR Constructions Hyderabad 29.60 15.00 13.36 14.25 Feb-04 May-05 Sep-05 Completed
M30 Rehabilitation of road from Kalmala Junction to Kavital Satish – Tantia (JV) 50.00 18.00 21.22 30.23 Jul-03 Jan-05 Aug-06 Completed
M31 Rehabilitation of road from Kavital to Mudgal Maheshwar Naidu – Prakash (JV) 52.46 19.00 19.55 25.33 Jul-03 Feb-05 Oct-05 Completed
M32 Rehabilitation of road from Nanjumalige Circle in Mysore city to PWD KM 62.00 on Mysore-Manandavadi road. KNR Constructions Hyderabad 58.90 22.00 23.87 28.01 Feb-04 Dec-05 Jun-06 Completed
M33 Rehabilitation of road from Navalgund to Ron GVR Constructions Pvt Ltd, Chennai 44.36 17.00 27.02 29.90 Mar-05 Aug-06 Dec-07 Completed
M34 Rehabilitation of road from Ron to Kushtagi IVRCL Infrastructure & Projects Ltd, Hyderabad 52.31 20.00 25.38 31.83 Mar-05 Nov-06 Apr-07 Completed
U9 Upgradation of road from Khanapur to Alnawar B. Seenaiah & Co.(Projects) Ltd, Hyderabad 35.24 17.00 27.03 23.42 Mar-05 Aug-06 Feb-09 Completed
U10 Upgradation of road from Hulikatti to Nargund GVR Constructions Pvt Ltd,Chennai 20.67 14.00 19.62 18.25 Mar-05 May-06 Jul-08 Completed
M4-A Rehabilitation of road Kagwad to Maharashtra Border S.F.Chougule, Sangli 2.50 5.00 1.30 2.66 Jun-06 Feb-07 Jun-07 Completed
M4-R Improvement of road from Kamatnur to NH-4 and Improvement of Distressed road from Chikodi to Sankeshwar T.K.Rajan,Mangalore 24.36 6.00 6.95 6.81 Jun-06 Mar-07 Mar-07 Completed
M32-A Improvements of road on Mysore - Manathwadi in Mysore DistM32A(PWD Km 62 to PWD KM 92+500) KNR Constructions, Hyderabad 30.50 5.00 11.58 13.14 Apr-07 Dec-07 Feb-10 Completed
    Total Length 2434.79              
Less Distressed road in M4 Package taken under M4-R   21.26              
    Total Length 2413.53              
Less Length of 19 Kms within Anshi National Park in Uttara Kannada District deleted from M27 Package (Rehabilitaiton)   19              
  Length of 10 Kms in Rajiv Gandhi National Park (Nagarahole) area is deleted from M32A Package (Rehabilitation)   10              
    Total Revised Length 2384.53              



KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT-I (KSHIP-I)

The PIU, KSHIP is a Unit of PWD set up in 1999-2000 which is responsible for the implementation of all Externally-aided SH Projects in Karnataka. It is headed by the Chief Project Officer rank of IAS / EIC and the Project Director of the rank of Chief Engineer who report administratively to the Principal Secretary / Additional Chief Secretary, PWD through Secretary, PWD

Karnataka State Highways Improvement Project –I

The Karnataka State Highways Improvement Project –I (KSHIP-1) was the first major initiative of the Public Works Department (PWD) of Government of Karnataka (GOK) for improvement of Road network of the state with external assistance during 1999.   The PWD carried out Strategic Option Study (SOS) on a road network of 13,362 kms through an Independent Consultant during 1996 and study identified 2888 kms comprising of State Highways (SH) and Major District Roads (MDR) roads for prioritised improvements.

 

The Karnataka Highways Improvement Project, KSHIP-I was launched by Karnataka Government in the year during 1999-2000 vide G.O. No. PWD 21 CRM 96, dated 01.07.1999.KSHIP-I has been implemented with the financial assistance of the International Bank for Reconstruction & Development (IBRD) (The World Bank) in line with the Project & Loan Agreement no 4606 IN dated 21-07-2001. The original cost of the project was Rs.2030.27 Crore, which includes World Bank loan of Rs.1635.21 crore (US $ 360.00 million) being 80% of the project cost.  The Project cost has been revised from Rs. 2030.27 crore to Rs. 2390.00 crore.  The Project Completion Date was also extended from 30-06-2006 to 31-08-2011 and that of loan closing date extended from 31-12-2006 to 31-01-2008.

 

After carrying out feasibility study, development of about 2414 Kms were taken up during the period of 2001- 2008. The Improvement was carried out in two categories:

:

  • Upgradation-900 kms: involved Reconstruction of existing carriage way to the specified new width of 7.00 m carriage way with 1.00 m wide paved shoulders and 1.5 mt earthen shoulders on  both sides with a total formation width of 12.00 mts.
  • Rehabilitation-1514 kms: involved Improvement for the existing width of carriageway or 5.50 meters, whichever is higher without geometrical improvements and reconstructing the widened portion of carriageway

The total project length of 2414 Kms was taken up for improvement under 50 contract packages. A total length of 2385 kms in 49 contracts were completed (excluding 29 kms passing in forest areas due to court interventions). One Contract i.e Construction of Bridge across the Bennithora river (U3-BR) near Gulbarga was terminated for the poor performance of contractor and was handed over to NH for completing the balance work.

The Loan Agreement closed on 31-01-2008 with 100% utilization of the World Bank loan. 

Project Details:

Description Upgradation Rehabilitation Bridges Bypasses
(upgradation)
Total
Total No. of packages 10 35 3** 2 50
Original Project length in Km 885 1514 - 15 2414
Revised Project length in Km 885 1485** - 15 2385

**Note:

Length of 19 Kms within Anshi National Park in Uttara Kannada District deleted from M27 Package (Rehabilitation)

Length of 10 Kms in Rajiv Gandhi National Park (Nagarahole) area is deleted from M32A Package (Rehabilitation)

 1 Bridge work handed over to NH for completing the balance work.

The physical and financial achievements from the commencement of the project are as under.

Year

Physical in Kms

Financial                  Rs. in crore

2001-02

-

69.85

2002-03

191

161.23

2003-04

366

231.53

2004-05

510

480.26

2005-06

666

541.35

2006-07

449

524.62

2007-08

132

194.80

2008-09

40

73.14

2009-10

30

66.90

2010-11

-

15.52

2011-12

Nil

2.89

2012-13

1

4.56

2013-14

-

2.53

2014-15

-

1.69

2015-16

-

2.56

2016-17

-

0.83

2017-18

-

1.61

2018-19

 

0.66

2019-20

 

4.51

2020-21

 

1.72

2021-22

 

2.32

2022-23

 

1.63

2023-24   6.16

Total

2385

2392.87

 

*inclusive of front end fee of Rs.16.35 cr

The performance of KSHIP-1 received the appreciation of the World Bank in its Portfolio Review of Karnataka in June 2005. The WB has assessed progress of KSHIP as far higher than National Average and on par with the Bank’s worldwide average. The KSHIP has also bagged the India-Tech Excellence Award-2010 as the 2nd Best Implemented Infrastructure Project in India and the award was presented by the President of India on 27th Oct 2010..

India-Tech Excellence Award-2010 function

India-Tech Excellence Award-2010 function.

Her Excellency, Smt.Prathibha Patil, President of India presenting the award to PIU-KSHIP on 27th Oct 2020 

India-Tech Excellence Award-2010 function

Sri.B.H.AnilKumar I.A.S, Chief Project Officer

Sri.N.L.R.Peshve , Secretary ,PWD

Sri. K.S.Krishna Reddy, Project Director, KSHIP

At India-Tech Excellence Award-2010 function.

Note: Mouse over on the map to zoom



WAP-1 : Malavalli to Pavagada
Road Length: 194.34 Km ; Duration: 30 Months Construction + 90 Months Maintenance
Construction Cost: Rs 576 Crores ; Annuity Cost(Biannual): Rs 1306 Cr(239 Cr + 15 Installments of Rs 71.15 Cr)
Construction Schedule: 06-Nov-2014 to 06-May-2017
Executing Agency: M/S Mysore Bellary Pvt Ltd(M/S Sadbhav-GKC(JV))
Construction Supervision Consultant: M/S LEA Associates South Asia Private Ltd
WAP-2 : Mudhol to Nippani
Road Length: 107.94 Km ;   Duration: 24 Months Construction + 96 Months Maintenance
Construction Cost: Rs 331 Crores ; Annuity Cost(Biannual): Rs 768 Cr(136 Cr + 16 Installments of Rs 39.49 Cr)
Construction Schedule: 19-Jan-2015 to 19-Jan-2017
Executing Agency: M/S Ashok Buildcon-GVR(JV)
Construction Supervision Consultant: M/S Aarvee Associates Architects Engineers& Consultants Pvt Ltd
WAEP-3A : Shimoga-Shikaripura-Anandapuram
Road Length: 82 Km ;   Duration: 32 Months
Construction Cost: Rs 264.73 Crores ; Construction Schedule: 28-4-2015 to 27-12-2017
Executing Agency: M/S Patel Engineering Pvt Ltd
Construction Supervision Consultant: M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd
WAEP-3B : Shikaripura-Anavatti-Hangal
Road Length: 71.63 Km ;   Duration: 29 Months Construction
Construction Cost: Rs 224.7 Crores ; Construction Schedule:
Executing Agency: M/S RNS Infrastructure Ltd
Construction Supervision Consultant: M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd
WAEP-4 : Managuli-Devapura
Road Length: 109.953 Km ;   Duration: 33 Months Construction
Construction Cost: Rs 317.05 Crores ; Construction Schedule:
Executing Agency: M/S Sadbhav Engineering Ltd
Construction Supervision Consultant: M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd.
WEP1 : Hoskote to Chintamani Bypass of SH-82
Road Length: 52.4 Km ;   Duration: 30 Months
Contract Amount: Rs 98.22 Crores
Schedule: 13-Aug-2011 to 12-Feb-2014
Executing Agency: M/s Lanco Infratech Ltd
Construction Supervision Consultant: EGIS International
WEP2a : Haveri to Hanagal SH-2
Road Length: 31.784 Km ;   Duration: 21 Months
Contract Amount: Rs 92.54 Crores
Schedule: 02-Mar-2013 to 22-Dec-2014
Executing Agency: M/s DRN Infrastructure, Hubli
Construction Supervision Consultant: EGIS International
WEP2b : Hanagal to Tadasa of SH-1, SH-2
Road Length: 43.476 Km ;   Duration: 21 Months
Contract Amount: Rs 97.87 Crores
Schedule:
Executing Agency: M/S DRN Infrastructure
Construction Supervision Consultant: EGIS International
WEP3 : Dharwad to Saundatti of SH-34
Road Length: 36 Km ;   Duration: 41 Months
Contract Amount: Rs 84.44 Crores
Schedule: 28-Jul-2011 to 01-Dec-2014
Executing Agency: M/s RVCPL-RIDL JV
Construction Supervision Consultant: EGIS International
WEP4 : Tinthni to Kalmala of SH-61 & SH-15
Road Length: 73.80 Km ;   Duration: 36 Months
Contract Amount: Rs 160.79 Crores
Schedule: 13-Aug-2011 to 12-Aug-2014
Executing Agency: M/s Patel Engineering Ltd
Construction Supervision Consultant: EGIS International
WEP5 : Chowdapur to Gulbarga of SH-22
Road Length: 28.63 Km ;   Duration: 21 Months
Contract Amount: Rs 61.55 Crores
Schedule: 19-Jul-2011 to 18-Apr-2013
Executing Agency: M/s SRK-KCL JV
Construction Supervision Consultant: EGIS International
AEP1 : Magadi to NH-48 to Koratagere in Tumkur and Ramanagara Districts
Road Length: 68.20 Km ;   Duration: 33 Months
Contract Amount: Rs 116.69 Crores
Schedule: 21-Mar-2012 to 20-Dec-2014
Executing Agency: M/s. KNR Constructions Ltd
Construction Supervision Consultant: SMEC International
AEP2 : Pavagada to AP Border of SH-3
Road Length: 23.205 Km ;   Duration: 18 Months
Contract Amount: Rs 43.30 Crores
Schedule: 29-Mar-2012 to 28-Sep-2013
Executing Agency: M/s. GVR-RMN (JV)
Construction Supervision Consultant: SMEC International
AEP3 : Gubbi to Mandya of SH-84
Road Length: 108.62 Km ;   Duration: 33 Months
Contract Amount: Rs 196.81 Crores
Schedule: 21-Mar-2012 to 06-Dec-2014
Executing Agency: M/s. KMC-VDB (JV)
Construction Supervision Consultant: SMEC International
AEP3A : Gubbi-Beeragonahalli (near Yediyur) of SH-84
Road Length: 49.03 Km ;   Duration: 21 Months
Contract Amount: Rs 122.38 Crores
Schedule:
Executing Agency: M/S DRN Infrastructure, Hubli-30
Construction Supervision Consultant: SMEC International
AEP3B : Beeragonahalli (near Yediyur) - Mandya of SH-84
Road Length: 59.09 Km ;   Duration: 33 Months
Contract Amount: Rs 198.27 Crores
Schedule:
Executing Agency: M/S D.P Jain & Co Infrastructure Pvt Ltd
Construction Supervision Consultant: SMEC International
AEP4 : Jaglur to NH-13 and from SH-19 of KSHIP Road to Molakalmuru of SH-2
Road Length: 14.38 Km ;   Duration: 15 Months
Contract Amount: Rs 31.26 Crores
Schedule: 21-Mar-2012 to 21-Jun-2013
Executing Agency: M/s. GVR-RMN (JV)
Construction Supervision Consultant: SMEC International
AEP5 : Padubidri to Karkala of SH-1
Road Length: 27.80 Km ;   Duration: 18 Months
Contract Amount: Rs 61.27 Crores
Schedule: 05-Mar-2012 to 20-Sep-2013
Executing Agency: M/s. RNS Infrastructure Ltd
Construction Supervision Consultant: SMEC International
AEP6 : Davangere to Birur of SH-76
Road Length: 105.63 Km ;   Duration: 33 Months
Contract Amount: Rs 202.57 Crores
Schedule: 21-Mar-2012 to 20-Dec-2014
Executing Agency: M/s.Gammon India Ltd
Construction Supervision Consultant: SMEC International
AEP6A : Davangere to Channagiri of SH-76
Road Length: 53.65 Km ;   Duration: 21 Months
Contract Amount: Rs 181.45 Crores
Schedule: 15-Dec-2015 to 15-Sep-2017
Executing Agency: M/S JMC Projects (India) Ltd.
Construction Supervision Consultant: SMEC International
AEP6B : Chennagiri to Birur of SH-76
Road Length: 51.98 Km ;   Duration: 22 Months
Contract Amount: Rs 136.78 Crores
Schedule: 1-Sep-2015 to 1-Jul-2017
Executing Agency: M/s D P Jain & Co, Infrastructure Pvt. Ltd.,
Construction Supervision Consultant: SMEC International
AEP7 : Shelvadi to Mundargi of SH-45
Road Length: 63.44 Km ;   Duration: 33 Months
Contract Amount: Rs 121.25 Crores
Schedule: 21-Mar-2012 to 20-Dec-2014
Executing Agency: M/s. KNR Constructions Limited
Construction Supervision Consultant: SMEC International
AEP8 : Mudgal to Gangawathi of SH-29
Road Length: 74.20 Km ;   Duration: 36 Months
Contract Amount: Rs 152.63 Crores
Schedule: 26-Mar-2012 to 25-Mar-2015
Executing Agency: M/s. KNR Constructions Ltd
Construction Supervision Consultant: SMEC International
AEP9 : Soundatti to Kamatagi(including Mulur Ghat) of SH-34 and SH-14
Road Length: 130.13 Km ;   Duration: 36 Months
Contract Amount: Rs 225.50 Crores
Schedule: 21-Mar-2012 to 20-Mar-2015
Executing Agency: M/s. Ramky Infrastructures Ltd
Construction Supervision Consultant: SMEC International
AEP9A : Saundatti to Halagatti Junction(Ramdurga) (including Mullur ghat)
Road Length: 42.065 Km ;   Duration: 21 Months
Contract Amount: Rs 138.24 Crores
Schedule:
Executing Agency: M/S DP Jain & Co Infrastructure Pvt Ltd
Construction Supervision Consultant: SMEC International
AEP9B : Halagatti Junction(Ramdurga) to Badami(including Badami Bypass)
Road Length: 45 Km ;   Duration: 21 Months
Contract Amount: Rs 146.04 Crores
Schedule:
Executing Agency: M/S RNS Infrastructure Ltd
Construction Supervision Consultant: SMEC International
AEP9C : Badami Bypass junction - Pattadakallu - Kamatagi
Road Length: 43.13 Km ;   Duration: 21 Months
Contract Amount: Rs 110.89 Crores
Schedule:
Executing Agency: M/S Ashoka Buildcon Ltd
Construction Supervision Consultant: SMEC International
Last Updated: 29-Mar-2024 16:20