View Progress in Combine Lane KM      Countdown to Completion
Physical ProgressFinancial ProgressQuality
Ongoing Works
WAP1   View Administrative Status    Last 30 days' progress
Upgradation and maintenance of the Road from Malavalli (Km.0+000) to Pavagada (Km 193.344)
Road Length: 193.344Km Duration: 46 Months
Contract Amount: INR 239.00 Cr   Revised Contract Amount: INR239.00 Cr
Schedule: 24-Mar-2014 to 31-Dec-2017
WAP2   View Administrative Status    Last 30 days' progress
Up gradation of the Road from Mudhol (Km.0+000) to Nippani (Km 107.937)
Road Length: 107.937Km Duration: 33 Months
Contract Amount: INR 317.60 Cr   Revised Contract Amount: INR321.24 Cr
Schedule: 14-Mar-2014 to 11-Dec-2016
WAEP3A   View Administrative Status    Last 30 days' progress
Upgradation of Road from Shimoga(Km 0+000)-Shikaripura-Anandapuram(Km 82+040) of SH-1 and SH-57
Road Length: 82.04Km Duration: 30 Months
Contract Amount: INR 264.73 Cr   Revised Contract Amount: INR271.83 Cr
Schedule: 12-Oct-2015 to 11-Apr-2018
WAEP3B   View Administrative Status    Last 30 days' progress
Upgradation of the Road from Shikaripura( Km 0+000)-Anavatti-Hangal ( km 71+630) of SH-1
Road Length: 71.63Km Duration: 29 Months
Contract Amount: INR 224.71 Cr   Revised Contract Amount: INR276.79 Cr
Schedule: 01-Oct-2015 to 28-Feb-2018
WAEP4   View Administrative Status    Last 30 days' progress
Upgradation of the Road from Managuli( Km 0+000)-Devapura ( km 109+953) of SH-61 in the State of Karnataka.
Road Length: 109.953Km Duration: 33 Months
Contract Amount: INR 317.05 Cr   Revised Contract Amount: INR339.86 Cr
Schedule: 27-Jul-2015 to 26-Apr-2018
Completed Works
WEP1   View Administrative Status    [COMPLETED]
Upgradation of the Road from Hoskote (Km.0+000) to Chintamani Bypass (Km 52+400) of SH-82
Road Length: 52.4Km Duration: 46 Months
Contract Amount: INR 98.22 Cr   Revised Contract Amount: INR113.87 Cr
Schedule: 13-Aug-2011 to 12-Feb-2014
WEP2A   View Administrative Status    [COMPLETED]
Upgradation of the Road from Haveri (km 0+000) to Hanagal (km 31+784) of SH-2
Road Length: 31.784Km Duration: 41 Months
Contract Amount: INR 92.54 Cr   Revised Contract Amount: INR92.54 Cr
Schedule: 02-Mar-2013 to 01-Dec-2014
WEP2B   View Administrative Status    [COMPLETED]
Upgradation of the Road from Hanagal (Km 0+000) to Tadasa (Km 43+459) of SH-2
Road Length: 43.459Km Duration: 36 Months
Contract Amount: INR 97.87 Cr   Revised Contract Amount: INR98.22 Cr
Schedule: 20-Jul-2013 to 15-Apr-2015
WEP3   View Administrative Status    [COMPLETED]
Upgradation of the Road from Dharwad(Km 0+000) to Saundatti (Km 38+500) of SH-34
Road Length: 36Km Duration: 31 Months
Contract Amount: INR 84.44 Cr   Revised Contract Amount: INR84.45 Cr
Schedule: 28-Jul-2011 to 27-Jun-2013
WEP-3A   View Administrative Status    [COMPLETED]

Road Length: 2.5Km Duration: 0 Months
Contract Amount: INR 18.40 Cr   Revised Contract Amount: INR0.00 Cr
Schedule: 01-Dec-2017 to 31-Jul-2021
WEP4   View Administrative Status    [COMPLETED]
Upgradation of the Road from Tinthni (Km.0+000) to Kalmala (Km 73+800) of SH-61 & SH-15
Road Length: 73.8Km Duration: 46 Months
Contract Amount: INR 160.79 Cr   Revised Contract Amount: INR173.88 Cr
Schedule: 13-Aug-2011 to 12-Aug-2014
WEP5   View Administrative Status    [COMPLETED]
Upgradation of the Road from Chowdapur (Km.0+000) to Gulbarga (Km.28+630) of SH-22
Road Length: 28.63Km Duration: 33 Months
Contract Amount: INR 61.55 Cr   Revised Contract Amount: INR56.76 Cr
Schedule: 19-Jul-2011 to 18-Apr-2013
ADB
View Progress in Combine Lane KM      Countdown to Completion
Physical ProgressFinancial ProgressQuality
Ongoing Works
AEP-3A   View Administrative Status    Last 30 days' progress
Up-gradation of the Road from Gubbi( Km 0+000)- Beeragonahalli near Yediyur( km 49+030) of SH-84
Road Length: 49.03 Km Duration: 21 Months
Contract Amount: INR 122.39 Cr   Revised Contract Amount: INR159.93 Cr
Schedule:13-Dec-2015 to 31-Dec-2017
AEP-3B   View Administrative Status    Last 30 days' progress
Upgradation of the Road from Beeragonahalli near Yediyur( Km 0+000)- to Mandya( km 59+590) of SH-84
Road Length: 59.59 Km Duration: 21 Months
Contract Amount: INR 198.27 Cr   Revised Contract Amount: INR237.00 Cr
Schedule:09-Sep-2015 to 31-Dec-2017
AEP-6A   View Administrative Status    Last 30 days' progress
Upgradation of the Road from Davanagere (Km 0+000) to Channagiri (km 53+650) of SH-76 in the state of Karnataka.
Road Length: 52.27 Km Duration: 21 Months
Contract Amount: INR 181.45 Cr   Revised Contract Amount: INR210.60 Cr
Schedule:15-Dec-2015 to 30-Jun-2018
AEP-6B   View Administrative Status    Last 30 days' progress
Up gradation of the Road from Chennagiri( Km 0+000)- Birur( km 51+980) of SH-76
Road Length: 50.58 Km Duration: 19 Months
Contract Amount: INR 136.78 Cr   Revised Contract Amount: INR152.20 Cr
Schedule:05-Nov-2015 to 31-Mar-2018
AEP-9A   View Administrative Status    Last 30 days' progress
Upgradation of Road from Saundatti to Ramdurga (including Mullur ghat realignment) (Km 0+000 to Km 38+465) in link 21C and Ramdurga to Halgatti Junction,Ramdurga(Km 0+000 to Km 3+600) in link 21D
Road Length: 42.065 Km Duration: 25 Months
Contract Amount: INR 138.24 Cr   Revised Contract Amount: INR165.63 Cr
Schedule:24-Sep-2015 to 30-Dec-2017
AEP-9B   View Administrative Status    Last 30 days' progress
Upgradation of the road from Halagatti Junction( Ramdurga , km(3+600) to Badami(Km45+730) in Link 21-Dand from Badami to Badami Bypass Junction(km 0+000 to Km 2+870), in Link 21-E
Road Length: 43.58 Km Duration: 21 Months
Contract Amount: INR 146.05 Cr   Revised Contract Amount: INR170.03 Cr
Schedule:04-Sep-2015 to 28-Feb-2018
AEP-9C   View Administrative Status    Last 30 days' progress
Upgradation of Road from Badami Bypass junction (Km 2+870) to Pattadakallu (Km 21+530) in link 21E and Pattadakallu (Km 0+000) to Kamatagi (Km 22+280) link 21F including additional length for Badami bypass (2.190 kms) in link 21E
Road Length: 43.13 Km Duration: 21 Months
Contract Amount: INR 110.90 Cr   Revised Contract Amount: INR138.58 Cr
Schedule:24-Sep-2015 to 30-Oct-2017
ROB-1   View Administrative Status    Last 30 days' progress
Construction of ROB with approaches at Railway Km. 316/200-300, road Chainage 7+695 on Davanagere - Channagiri road (LC NO: 193 on Hubli - Chikjajur junction between Tholahunse - Davanagere Stations of Mysore Division)
Road Length: 1.38 Km Duration: 24 Months
Contract Amount: INR 41.00 Cr   Revised Contract Amount: INR47.11 Cr
Schedule:27-Nov-2014 to 31-Dec-2017
ROB-2   View Administrative Status    Last 30 days' progress
Construction of ROB with approaches at Railway Km-219/200-220/000, Road Chainage Km-44+855 on Channagiri - Birur road (LC No: 133 between Birur station - Nagavanagala station on Birur junction - Chikjajur section stations of Mysore Division
Road Length: 1.4 Km Duration: 24 Months
Contract Amount: INR 40.10 Cr   Revised Contract Amount: INR38.92 Cr
Schedule:07-Mar-2015 to 31-Mar-2018
ROB-3   View Administrative Status    Last 30 days' progress
Construction of ROB with approaches at Railway Km-55/200-300, Road Chainage Km25+339 on Gadag Bypass b/w Bennakatti - Gadag Stations on Huballi - Gadag Section
Road Length: 1.55 Km Duration: 24 Months
Contract Amount: INR 22.66 Cr   Revised Contract Amount: INR24.63 Cr
Schedule:28-Apr-2014 to 31-Oct-2016
ROB-4   View Administrative Status    Last 30 days' progress
Construction of ROB with approaches at Railway Km-60/600-700, Road Chainage Km42+24 on Ramdurga - Badami road (LC No: 29E on Gadag - Bagalkote Section b/w LKY - BDM stations of Gadag Division
Road Length: 1.43 Km Duration: 24 Months
Contract Amount: INR 28.58 Cr   Revised Contract Amount: INR31.43 Cr
Schedule:12-Nov-2014 to 30-Apr-2017
Completed Works
AEP1   View Administrative Status    [COMPLETED]
Upgradation of the Road from Magadi(Km.0+000) to NH-48 to Koratagere (Km 68+200) in Link 64-C,D & E in Tumkur and Ramanagara Districts
Road Length: 68.2 Km Duration: 33 Months
Contract Amount: INR 116.69 Cr   Revised Contract Amount: INR123.31 Cr
Schedule:21-Mar-2012 to 31-Jan-2017
AEP2   View Administrative Status    [COMPLETED]
Upgradation of the Road from Pavagada (Km.0+000) to AP Border (Km 23+210) of SH-3
Road Length: 23.205 Km Duration: 31 Months
Contract Amount: INR 43.30 Cr   Revised Contract Amount: INR43.30 Cr
Schedule:29-Mar-2012 to 31-Dec-2013
AEP4   View Administrative Status    [COMPLETED]
Upgradation of the Road from Jaglur(km 0+000) to NH-13(km 9+250) and from SH-19 of KSHIP(km 0+000) Road to Molakalmuru(5+130 Kms) of SH-2
Road Length: 14.38 Km Duration: 36 Months
Contract Amount: INR 31.26 Cr   Revised Contract Amount: INR33.62 Cr
Schedule:21-Mar-2012 to 20-Jun-2013
AEP5   View Administrative Status    [COMPLETED]
Upgradation of the Road from Padubidri (Km.0+000) to Karkala (Km 27+800) of SH-1
Road Length: 27.8 Km Duration: 38 Months
Contract Amount: INR 61.27 Cr   Revised Contract Amount: INR69.04 Cr
Schedule:21-Mar-2012 to 15-Nov-2014
AEP7   View Administrative Status    [COMPLETED]
Upgradation of the Road from Shelvadi (Km.0+000) to Mundargi (Km 63+440) of SH-45
Road Length: 63.44 Km Duration: 44 Months
Contract Amount: INR 121.39 Cr   Revised Contract Amount: INR134.72 Cr
Schedule:18-Jul-2012 to 19-Mar-2015
AEP8   View Administrative Status    [COMPLETED]
Upgradation of the Road from Mudgal (Km0+000) to Gangawathi (Km74+200) of SH-29
Road Length: 74.2 Km Duration: 35 Months
Contract Amount: INR 152.63 Cr   Revised Contract Amount: INR152.65 Cr
Schedule:26-Mar-2012 to 25-Mar-2015
Terminated Works
AEP3   View Administrative Status    [TERMINATED] Last 30 days' progress
Upgradation of the Road from Gubbi (Km.0+000) to Mandya (Km 108+620) of SH-84
Road Length: 108.62 Km Duration: 34 Months
Contract Amount: INR 196.81 Cr   Revised Contract Amount: INR196.81 Cr
Schedule:21-Mar-2012 to 20-Dec-2014
AEP6   View Administrative Status    [TERMINATED] Last 30 days' progress
Upgradation of the Road from Davangere (Km.0+000) to Birur(Km 105+630) of SH-76
Road Length: 105.63 Km Duration: 39 Months
Contract Amount: INR 202.57 Cr   Revised Contract Amount: INR202.57 Cr
Schedule:21-Mar-2012 to 30-Jun-2015
AEP9   View Administrative Status    [TERMINATED] Last 30 days' progress
Upgradation of the Road from Soundatti (Km0+000) to Kamatagi (Km 130+130) (including Mulu Ghat) of SH-34 and SH-14
Road Length: 130.13 Km Duration: 36 Months
Contract Amount: INR 225.50 Cr   Revised Contract Amount: INR225.50 Cr
Schedule:21-Mar-2012 to 20-Mar-2015