Present Works (KSHIP II) - Progress Summary View Progress

Package Description of Road Length (kms) Contract Value (INR Crores) Contractor Supervision Consultant  
World Bank Annuity Projects
WAP1 Up gradation of the Road from Malavalli (Km 0+000) to Pavagada (Km 193+34)
Duration: 30 Months Construction + 90 Months Maintenance
193.34 Construction Cost:Rs 559Cr + Annuity Cost(Biannual):Rs 1306 Cr(239Cr + 15 Installments of Rs 71.15Cr) M/S Mysore Bellary Pvt Ltd(M/S Sadbhav-GKC(JV)) M/S LEA Associates South Asia Private Ltd R&R LAQ EMP Work Progress
WAP2 Up gradation of the Road from Mudhol (Km 0+000) to Nippani (Km 107+94)
Duration: 24 Months Construction + 96 Months Maintenance
107.937 Construction Cost:Rs 317.60Cr + Annuity Cost(Biannual):Rs 768 Cr(136 cr + 16 Installments of Rs 39.49 Cr) M/S Ashok Buildcon-GVR(JV) M/S Aarvee Associates Architects Engineers & Consultants Pvt Ltd R&R LAQ EMP Work Progress
WAEP-3A Upgradation of Road from Shimoga(Km 0+000)-Shikaripura-Anandapuram(Km 82+040) of SH-1 and SH-57
Duration: 32 Months
82 264.73 M/S Patel Engineering Pvt Ltd, Mumbai M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd. R&R LAQ EMP Work Progress
WAEP-3B Upgradation of the Road from Shikaripura(Km 0+000)-Anavatti-Hangal (Km 71+630) of SH-1
Duration: 29 Months
71.63 224.7 M/S RNS Infrastructure Ltd., Naveen Complex,
 14 M.G.Road, 
Bangalore-560001
M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd. R&R LAQ EMP Work Progress
WAEP-4 Upgradation of the Road from Managuli(Km 0+000)- Devapura(Km 109+953) of SH-61
Duration: 33 Months
109.953 317.05 M/S Sadbhav Engineering Ltd., Sadbhav House, Opp. Law Garden Police Chowki, Ellisbridge, Ahmedabad 380006 M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd. R&R LAQ EMP Work Progress
  Total road length(World Bank Annuity Projects)  565.86        
World Bank Assisted EPC Projects View Work Progress
WEP1 Upgradation of the Road from Hoskote (Km.0+000) to Chintamani Bypass (Km 52+400) of SH-82
Duration: 30 Months
52.4 98.2 M/s Lanco Infratech Ltd M/s EGIS International R&R LAQ EMP Work Progress
WEP2A Upgradation of the Road from Haveri (km 0+000) to Hanagal (km 31+784) of SH-2
Duration: 21 Months
31.784 92.5 M/s DRN Infrastructure, Hubli M/s EGIS International R&R LAQ EMP Work Progress
WEP2B Upgradation of the Road from Hanagal(Km.0+000) to Tadasa(Km 43.476) of SH-1, SH-2
Duration: 21 Months
43.476 97.9 M/S DRN Infrastructure, Hubli M/s EGIS International R&R LAQ EMP Work Progress
WEP3 Upgradation of the Road from Dharwad(Km 0+000) to Saundatti (Km 38+500) of SH-34
Duration: 41 Months
36 84.4 M/s RVCPL-RIDL JV M/s EGIS International R&R LAQ EMP Work Progress
WEP4 Upgradation of the Road from Tinthni (Km.0+000) to Kalmala (Km 73+800) of SH-61 & SH-15
Duration: 36 Months
73.8 160.8 M/s Patel Engineering Ltd M/s EGIS International R&R LAQ EMP Work Progress
WEP5 Upgradation of the Road from Chowdapur (Km.0+000) to Gulbarga (Km.28+630) of SH-22
Duration: 21 Months
28.63 61.6 M/s SRK-KCL JV M/s EGIS International R&R LAQ EMP Work Progress
  Total road length(EPC)  266.09        
  Total road length (EPC + Annuity packages)  831.95        
Asian Development Bank Assisted Projects View Work Progress
AEP1 Upgradation of the Road from Magadi(Km.0+000) to NH-48 to Koratagere (Km 68+200) in Link 64-C,D & E in Tumkur and Ramanagara Districts
Duration: 33 Months
68.2 116.7 M/s. KNR Constructions Ltd M/s SMEC International R&R LAQ EMP Work Progress
AEP2 Upgradation of the Road from Pavagada (Km.0+000) to AP Border (Km 23+210) of SH-3
Duration: 18 Months
23.205 43.3 M/s. GVR-RMN (JV) M/s SMEC International R&R LAQ EMP Work Progress
AEP3A Upgradation of the Road from Gubbi( Km 0+000)- Beeragonahalli near Yediyur( km 49+030) of SH-84
Duration: 21 months
49.03 122.38 M/S DRN Infrastructure, Hubli-30 M/s SMEC International R&R LAQ EMP Work Progress
AEP3B Upgradation of the Road from Beeragonahalli near yediyur( Km 0+000)- to Mandya( km 59+590) of SH-84
Duration: 21 Months
59.59 198.27 M/S D.P Jain & Co. Infrastructure Pvt Ltd., Nagapur-440 001 M/s SMEC International R&R LAQ EMP Work Progress
AEP4 Upgradation of the Road from Jaglur(km 0+000) to NH-13(km 9+250) and from SH-19 of KSHIP(km 0+000) Road to Molakalmuru(5+130 Kms) of SH-2
Duration: 15 Months
14.38 31.3 M/s. GVR-RMN (JV) M/s SMEC International R&R LAQ EMP Work Progress
AEP5 Upgradation of the Road from Padubidri (Km.0+000) to Karkala (Km 27+800) of SH-1
Duration: 18 Months
27.8 61.3 M/s. RNS Infrastructure Ltd M/s SMEC International R&R LAQ EMP Work Progress
AEP6A Up gradation of the Road from Davanagere( Km 0+000)- Channagiri ( km 53+650) of SH-76
Duration: 21 Months
53.65 181.45 M/S JMC Projects (India) Ltd. M/s SMEC International R&R LAQ EMP Work Progress
AEP6B Upgradation of the Road from Channagiri (Km.0+000) to Birur(Km 51+980) of SH-76
Duration: 21 Months
51.98 136.78 M/s D P Jain & Co, Infrastructure Pvt. Ltd., M/s SMEC International R&R LAQ EMP Work Progress
AEP7 Upgradation of the Road from Shelvadi (Km.0+000) to Mundargi (Km 63+440) of SH-45
Duration: 33 Months
63.44 121.3 M/s. KNR Constructions Limited M/s SMEC International R&R LAQ EMP Work Progress
AEP8 Upgradation of the Road from Mudgal (Km0+000) to Gangawathi (Km74+200) of SH-29
Duration: 36 Months
74.2 152.6 M/s. KNR Constructions Ltd M/s SMEC International R&R LAQ EMP Work Progress
AEP9A Upgradation of Road from Saundatti to Ramdurga (including Mullur ghat realignment) (Km 0+000 to Km 37+270) in link 21C and Ramdurga to Halgatti Junction, Ramdurga(Km 0+000 to Km 3+600) in link 21D
Duration: 21 Months
42.065 138.24 M/S DP Jain & Co Infrastructure Pvt Ltd., U/6 Himalaya Accord Apartment, 
Opp Law college,
Amaravathi  Road
Nagapur-440 001
M/s SMEC International R&R LAQ EMP Work Progress
AEP9B Upgradation of the road from Halagatti Junction( Ramdurga , km(3+600) to Badami(Km45+730) in Link 21-D and from Badami to Badami Bypass Junction(km 0+000 to Km 2+870), in Link 21-E
Duration: 21 Months
45 146.04 M/S RNS Infrastructure Ltd., Naveen Complex,
 14 M.G.Road, 
Bangalore-560001
M/s SMEC International R&R LAQ EMP Work Progress
AEP9C Upgradation of Road from Badami Bypass junction (Km 2+870) to Pattadakallu (Km 21+530) in link 21E and Pattadakallu (Km 0+000) to Kamatagi (Km 22+280) link 21F including additional length for Badami bypass (2.190 kms) in link 21E
Duration: 21 Months
43.13 110.89 M/S Ashoka Buildcon Ltd., Ashoka House, Ashoka Marg, Ashoka Nagar, Nashik -422011 M/s SMEC International R&R LAQ EMP Work Progress
  Total road length(Asian Development Bank)  615.67       Work Progress
Road Over Bridge Projects
ROB-1 Construction of ROB with approaches at Railway Km-316/200-300, Road Chainage Km7+695 on Davangere - Channagiri road (LC No: 193 on Huballi - Chikjajur Junction b/w Tholahunse - Davanagere stations of Mysuru Division
Duration: 24 Months
- 39.79 M/S KNR Construction Ltd, Hyderabad, Andra Pradesh M/S SMEC International R&R LAQ EMP Work Progress
ROB-2 Construction of ROB with approaches at Railway Km-219/200-220/000, Road Chainage Km44+855 on Channagiri-Birur road (LC No: 133 on Birur station - Nagavanagala station on Birur junction - Chikjajur section stations of Mysuru Division
Duration: 24 Months
- 36.09 M/S Venkata Raju Engineers & Contractors, Vijayawad, Andra Pradesh M/S SMEC International R&R LAQ EMP Work Progress
ROB-3 Construction of ROB with approaches at Railway Km-55/200-300, Road Chainage Km25+339 on Gadag Bypass b/w Bennakatti - Gadag Stations on Huballi - Gadag Section
Duration: 24 Months
- 22.66 M/S KNR Construction Ltd, Hyderabad, Andra Pradesh M/S SMEC International R&R LAQ EMP Work Progress
ROB-4 Construction of ROB with approaches at Railway Km-60/600-700, Road Chainage Km42+24 on Ramdurga - Badami road (LC No: 29E on Gadag - Bagalkote Section b/w LKY - BDM stations of Gadag Division
Duration: 24 Months
- 28.58 M/S KNR Construction Ltd, Hyderabad, Andra Pradesh M/S SMEC International R&R LAQ EMP Work Progress
  Total road length  1447.62        



Present Works (KSHIP-II World Bank)

1. Government of Karnataka has now proposed to take up KSHIP- II to further improve state highways. Strategic Option Studies were carried out on l4,090 Km of State Highways. Feasibility studies were conducted on selected 4888 km roads. The selection of roads for preparation of Detail project report is based on ranking with 80 % weightage for economic internal rate of return and 20% weightage for Deprivation Index derived from Dr Nanjundappa committee report for redressal of regional imbalances. Finally, 3411 Km of State Highways are identified for improvement, which is approved by the Cabinet in Nov 2006. A Government Order was issued to notify the consultants to prepare DPR for selected 3411 kms vide No. PWD 61 EAP 2006 dated 25.11.2006. Consultants M/s.ScottWilson Ltd., U.K in Jv with Scottwilson India Ltd,Delhi have been appointed following World Bank norms to carry preparation of Detailed Project Reports (DPR).

2. The DPR is ready for 3411 Kms.

3. The Department of Economic Affairs, Govt. of India has recommended a loan assistance of US $ 300 million for the project of KSHIP-II from the World Bank.

Successive World Bank Missions headed by Mr. Binyam Reja have visited the project and the state to review the progress of the Project Preparation and to discuss and agree on the remaining Project preparation activities and timeline for project Appraisal and approval of the proposed Karnataka State Highway Improvement Project –II (KSHIP-II). A road length of 831 Kms is proposed for improvement under Stage-I of KSHIP-II with the World Bank financial assistance. Out of 831 kms, 269 kms are proposed for implementation through EPC mode and the remaining 562 kms through Annuity mode, The activities related to Land Acquisition, clearing of encumbrances and Environmental clearances etc are in progress.

4. The World Bank has also provided a Public Private Infrastructure Advisory Facility (PPIAF) grant of 44,000 US $ to provide technical assistance and advisory services to Govt.of Karnataka to develop roads under various Public Private Partnerships by raising resources from private sector, domestic financing and Viability Gap Funding(VGF) grant. The PPIAF consultant has Submitted draft report.

 

 

KSHIP-II THE WORLD BANK ASSISTANCE PROJECT (Stage-I)

 

The Department of Economic Affairs, Govt. of India has recommended a loan assistance of US $ 300 million for the Project of KSHIP-II from the World Bank. The status of the project is as below;

826 kms of State Highways have been finalized for upgradation to 2-lane under WB finance. The implementation is proposed to be under taken in two category of contracts viz EPC contracts (conventional item rate contract) and Annuity contracts. The list of roads is provided in the table below:

EPC Contracts:

Sl No. Link No Name of the link Length in kms Package No.
1 67A Hoskote - Hindgnala Cross 23.50 WEP-1
2 67B Hindgnala Cross - Chinatmani Bypass 29.00
Total 52.50
3 T8 Haveri (NH4) – Hangal 31.80 WEP-2A
4 M7D Hangal- Tadasa 43.50 WEP-2B
5 21B Dharwada – Saundatti 38.53 WEP-3
6 13A Tinthni – Devadurga 32.45 WEP-4
7 13B Devadurga - Kalmala 41.35
Total 73.800
8 6C Chowdapur - Gulbarga 28.67 WEP-5
Total road length under EPC 268.82  

The EPC contracts are regular ICB contracts with defects notification period of one year and the World Bank is expected to fund 80% of the contract cost.

Sl No. Link No Name of the link Length in kms Package No.
1 63A (NH209) Malavalli - Maddur 22.8 WAP-1
2 63B Maddur - Huliyurdurga 27.53
3 63C Huliyurdurga - Kunigal 21.11
4 63D Kunigal - Tumkur (NH206) 35.19
5 63E Tumkur - Koratagere 27.9
6 64F Koratagere - Madhugiri 20.03
7 64G Madhugiri - Pavagada 35.79
Total 193.344
8 19A Mudhol - Mahalingapura 19.17 WAP-2
9 19B Mahalingapura - Kabbur 42.35
10 19C Kabbur - Chikkodi 18.41
11 19D Chikkodi - Nippani (NH4) 28.0
Total 107.93
12 T21 Shikaripura - Anandapuram (NH206) 32.24 WAEP-3A
13 M7A Shimoga - Shikaripura 49.8
Total 82.04
14 M7B Shikaripura - Anvatti 53.0 WAEP-3B
15 M7C Anvatti - Hangal 18.63
Total 71.63
16 10A Managuli - Basavana Bagewadi - Talikota 61.31 WAEP-4
17 10B Talikota - Hunasagi - Devapur 48.66
Total 109.97
Total road length under Annuity 561.92  

The Annuity Contracts would be of 10 years duration with max. of 3 years of construction and 7 years of maintenance. Under Annuity Concession Contracts, it is proposed to avail the World Bank assistance for an upfront payment of 50% of the construction cost and the remaining payments during the maintenance period of 7 years on annuity basis to be met out of State funds.

Bids for EPC contracts have been invited. Bids were opened on 01-06-2010. The bid evaluation at PIU has been completed and the World Bank clearance for the Bid Evaluation Report is expected shortly. The contractors for the five EPC contract works are expected to be mobilized after the clearance of the World Bank in December 2010.

Mobilisation process of Construction Supervision Consultancy Services for EPC contracts is initiated and Banks no objection to Technical Evaluation of RFP is received. Financial proposals are to be opened shortly.

Bid documents for procurement of Annuity Contracts are under finalization in consultation with the World Bank. The clearance of the Bank is expected by January 2011.

Mobilisation of Transaction Advisory Consultancy Services for procurement of Annuity contracts has been initiated.

Pre-project activities of Land acquisition, R&R issues, Shifting of utilities, environmental issues for the entire length of 826 kms are undertaken as per World Bank norms. Provisions of KSHA 1964 has been adopted for land acquisition under the project.

Removal of encumbrances for the EPC roads is in advanced stage of completion.




Present Works (KSHIP II - Asian Development Bank - ADB)

Asian Development Bank Assistance Project (Stage-II)

Based on the recommendation of GOI, ADB has proposed to fund US$ 300 million for the KSHIP-II project from the year 2010.

ADB Mission has visited KSHIP on the following dates to review the project preparatory activities.

 

  1. November 2008 – Contact Mission.
  2. March 2009 – Consultation Mission.
  3. February 2010 – Inception Mission.
  4. May 2010 – Loan Reconnaissance Mission.
  5. August 2010 - Loan fact finding Mission

 

ADB Mission has proposed the following tentative timeline schedule for processing the proposed project as under.

 

  • Loan Negotiations - October 2010
  • Board Consideration - November 2010
  • Agreement Signing - March, 2011
  • Loan Effectiveness - May 2011

 

Based on advanced preparedness of KSHIP, ADB has advanced loan processing to 2010-11 instead of 2011-12.

Loan negotiation process is attended during 29-30th October 2010.

ADB has finalized 634 kms of prioritized State Highways for development out of 3411 kms of roads in KSHIP-II.

The list of roads shortlisted for ADB Projects are:

Sl. No. Package No. Link ID Link Name Length in Kms Total Length Kms
1 AEP-1 64C
64D
64E
Magadi NH 48– Dobbaspet – Koratagere 13.88
20.44
33.86
68.2
2 AEP-2 64H Pavagada to AP Border 23.205 23.205
3 AEP-3A 57A Gubbi to Beeragonahalli near Yediyur 49.03 49.03
4 AEP-3B 57B
57C
Beeragonahalli near Yediyur to Mandya 59.59 59.59
5 AEP-4 T13
T17
Jagaluru NH-13
About 5 Km from SH-19 (KSHIP Road)
9.25
5.13
14.38
6 AEP-5 48A Padubidri-Karkala 27.80 27.80
7 AEP-6A 42A Davangere to Channagiri 53.63 53.63
8 AEP-6B 42B Channagiri to Birur 51.98 51.98
9 AEP-7 27A
27B
Shelvadi-Gadag-Mundagi
 
30.540
33.64
63.44
10 AEP-8 31A
31B
Mudgal-Tavaragere
Kanakagiri-Gangawathi
31.21
43
74.21
11 AEP-9A 21C
21D
Saundatti to Ramdurga
Ramdurga to Halagatti Junction
20.000
22.065
42.065
12 AEP-9B 21D
21E
Halagatti Junction(Ramdurga) to Badami
Badami to Badami Bypass Junction
21.53
33.36
45
13 AEP-9C 21E
21F
21E
Badami Bypass junction to Pattadakallu
Pattadakallu to Kamatagi
Badami Bypass
15.13
15.53
12.47
43.13
Total   615.17

Action taken and the present status:

Preliminary activities like utility shifting, land acquisition and R & R are under progress.

Statutory Environmental clearances:

NOC obtained from Karnataka State Pollution Control Board
Awaiting clearance from SIEAA
Forest diversion permission - Under progress
Tree Cutting – Under progress

Bidding Documents of procurement

Bidding document (contract conditions) for civil works is submitted to ADB for review. ADB has communicated the comments on the bid documents and compliance to the same are prepared. Modified bid documents attending the comments submitted to ADB.

RFP document for Consultancy Supervision Consultant is submitted to ADB for review. ADB has communicated the comments on the RFP document twice earlier and the same were attended. Modified RFP document after attending the recent comments is submitted to ADB. EOI evaluation is under progress.

Procurement plan for ADB project is submitted to ADB.

As per the tentative programme schedule bids will be invited during December 2010 and contracts will be awarded during April 2011.

Report and Recommendation of President (RRP), PAM and other documents are finalized.

Terms of reference for Piggy-Back CDTA, PRAMC, S-PATA are finalized.

ADB has intimated Loan Negotiation date as 28-29 October, 2010.

Government Order has been issued towards approval of ADB project.

SLCC approval to ADB project has been received.

Asian Development Bank has provided US$ 1.5 Million as grant from the Japan special fund to carry out CDTA studies. M/s. Scott Wilson India Pvt. Ltd., is the consultant and the task assigned are:

A. Preparing master plan for the road sector.
B. Establishing & Strengthening of KSHTTA in master planning work.
C. PWD Institutional Strengthening for road sector maintenance, improvement, training.

The consultancy work is under progress. The consultant has submitted interim report on the components A, B, C.

Workshop conducted on 22.11.2010 towards review, PWD opinion for the finalization of proposed CRN.



Land Acquisition Status of Annuity Contracts (World Bank)

Back As on 31-Oct-2014
Sl. No. Package. No. Name of the Link Link No. Total No. of Sy.No. Total Extent U/s 15
A - G
Possession Taken U/s19 Extent & No. of Sy.No. & Date Compensation Paid Court deposit process General Award Sy. No. Total Balance to be paid Remarks Prince Negotiation Meeting conducted dates
Extent
A -G
Sy.No. Sy.No. Sy.No. Sy.No. Sy.No.
1 WAP 1 (NH209) Malavalli - Maddur 63-A 115 8-28 8-28
(115)
Completed
07-02-2013
1-13 1/4 15 - - 15 100 Payment under progress 27.06.2014 &,
28.06.2014
2 Maddur - Huliyurdurga 63-B 411 15-07 1/2 14-01
(411)
Completed
03-11-2013
0-26 1/2 25 - - 25 386 Payment under progress 18.05.2013,
20.06.2014,
23.06.2014&
25.06.2014
13.08.2014
14.08.2014
3 Huliyurdurga - Kunigal 63-C 202 13-33 1/4 13-33
(202)
Completed
09-11-2012/td>
3-12 1/4 37 - - 37 165 Payment under progress 18.02.2013
4 Huliyurdurga bypass 63-BC 73 23-33 23-22 3/4
(73)
Completed
24-09-2013
- - - - - 73 Price Negotiation Meeting date awaited from AC (SDM) Price negotiation meeting to be conducted.
5 Kunigal - Tumkur (NH206) 63-D 185 13-22 1/2 13-14
(185)
Completed
20-09-2012
08.01.2014
3-05 3/4 73 - - 73 112 Payment under progress 15-03-2013,
18-05-2013
6 Tumkur - Koratagere 63-E 60 8-35 3/4 8-23 1/4
(60)
Completed
09-11-2012
7-31 12 - 41 53 7 U/s. 19 Additional Notification and submitted to Government 01.07.2014 14-06-2013
7 Koratagere - Madhugiri 63-F 72 4-18 3/4 4-17 1/2
(72)
Completed
03-11-2012
3-17 3/4 14 - 48 62 10 Payment under progress 14-06-2013
13-06-2013
10-06-2014
8 Madhugiri Bypass 63-FG 172 54-18 1/4 54-18 1/4
(-172)
Completed
28-12-2012
5-05 3/4 14 - - - 172 Payment under progress 27.05.2014 & 28.05.2014
(U/s 15 Notification addl. Sent to Govt on 08.10.2013)
Total 1336 148-05 3/4 145-29 1/4
(1336)
25-20 1/2 183 - 128 311 1025
1 WAP 2 Mudhol - Mahalingapura 63-FG 172 54-18 1/4 54-18 1/4
(-172)
Completed
28-12-2012
5-05 3/4 14 - - - 172 Payment under progress 27.05.2014 & 28.05.2014
(U/s 15 Notification addl. Sent to Govt on 08.10.2013)
2 Mahalingapura - Kabbur 19-B 352 44-01 1/4 43-33 3/4
(352)
Completed
31-08-2013
19.06.2014
6-10 1/4 75 - - - 277 08.01.2014
27.01.2014
24.01.2014
3 Kabbur - Chikkodi 19-C 39 4-22 4-17
(39)
Completed
01-02-2013
4-12 1/2 6 - 32 38 1 21.01.2014
4 Chikkodi - Nippani (NH4) 19-D 155 22-37 1/2 21-33 1/2
(155)
Completed
01-02-2013
20-21 1/2 20 - 135 155 0 21.01.2014
22.01.2014
Total 663 88-09 1/2 75-39 3/4
(663)
36-24 1/4 140 - 239 379 284
Grand Total 1999 236-15 1/4 222-07 1/24
(1999)
62-04 3/4 323 - 367 1309



List of World Bank Consultancies working for KSHIP-II

Sl No Supervision Consultant Description Contract Value (in INR) Start Date End Date Status
1 M/s EGIS International Ltd. In JV with EGIS-India and Aarvee Associates Construction Supervision Consultants for the Supervision of Construction and Contract Administration of the 5 EPC Contracts Rs 35,15,00,274 26-04-2011 30-09-2016 Completed
2 M/s ROUGHTON INTERNATION LTD. United Kingdom
is associated with M/s SATRA INFRASTRUCTURE MANAGEMENT SERVICES
Construction Supervision Consultants for the Supervision of Construction and Contract Administration of the 3 Annuity Coverted EPC Contracts (WAEP-3A, WAEP-3B & WAEP-4) Rs 19,55,37,136 06-07-2015 06-04-2019 In progress
3 URS Scott Wilson Bangalore Consultancy Services for Preparing of Detailed Project Reports for all WB & ADB packages Rs 80,00,000 01-01-2016 31-12-2016 Completed
Consultancy Services for Preparing of Detailed Project Reports for all WB & ADB packages Rs 80,00,000 01-01-2017 31-12-2017 In progress
4 M/s LEA Associates South Asia Independent Engineer (IE-1) for the Monitoring of WAP-1 Annuity Contract Package Rs 21,10,45,689 12-12-2014 10-06-2017 In progress
5 M/s Aarvee Associates Architect engineers & consultants Independent Engineer (IE-2) for the Monitoring of WAP-2 Annuity Contract Package Rs 13,71,99,100 19-01-2015 19-09-2017 In progress
6 M/s Allied Boston Consultancy India Pvt Ltd, New Delhi. QM/ISO certification- Documentation/manual preparation services (II Phase) Rs 1,69,40,000 17-11-2014 16-12-2016 In progress
7 M/s Allied Boston Consultancy India Pvt Ltd, New Delhi. Consultancy services for operationalisation of Environment Management System(EMS) ISO 14001 in KPWD Rs 71,01,000 26-11-2012 30-09-2017 In progress
8 M/s Indian Register Quality Systems, Bangalore Third Party Audit service for accreditation of ISO 14001-2004 to 14 KPWD offices Rs 18,11,956 16-3-2015 16-3-2018 In progress
9 M/s Vindhya e-Infomedia Pvt Ltd,Bangalore Establishment of Public Response Centre for PIU ,KSHIP Rs 49,43,959 13-10-2014 30-11-2016 Completed
Establishment of Public Response Centre for PIU ,KSHIP Suplimentary Agreement - 1 Rs 49,43,960 30-11-2016 13-01-2018 In progress
10 M/S Vicroads ,Australia Consultancy services to build Road Safety lead agency capacity in Transport Dept. Rs 7,65,00,000 10-1-2013 04-10-2015 Completed
11 M/s BIRDS NGO Services for Implementation of Resettlement Action Plan for North Karnataka Packages Rs 52,08,300 09-11-2009 31-12-2014 Completed
12 M/s Samaj Vikas M & E Consultants for Implementation of Resettlement Action Plan for both Packages Rs 38,48,136 09-11-2009 31-3-2015 Completed
13 M/s Centaur Informations Systems Pvt Ltd DBMS Consultant for LAQ & R&R Packages for KSHIP II Rs 11,82,800 12-07-2009 05-01-2014 Completed
14 M/s Simpro Business Solutions Pvt Ltd DBMS Consultant for LAQ & R&R Packages for KSHIP II Rs 7,21,200 07-01-2015 31-12-2015 Being Continued
15 M/s Mittal & Co., Chartered Accounts, Faridabad, Haryana Consultancy Services for Internal Audit of KSHIP-II Rs 8,00,000 15-11-2012 15-11-2013 Completed
16 M/s Patro & Co Consultancy Services for Internal Audit of KSHIP-II Rs 10,00,000 11-01-2014 31-12-2016 In progress
17 M/s Wipro Pvt Ltd,Bangalore IT/ICT/MIS enhancement services and action plan preparation and implementation Rs 67,25,559 05-01-2015 05-07-2016 Services to be extended
18 M/s Saxena Consultancy services for HRD training enhancements and program delivery in PWD Rs 27,00,000 27-3-2013 25-5-2014 Completed
19 M/s Backend Bangalore Pvt Ltd,Bangalore Consultancy services for PWD implementation of project management framework and processes Rs 1,36,98,750 21-10-2012 21-10-2015 Completed
Rs 60,24,266 21-10-2015 31-12-2017 In Progress
20 M/s Gaurish Technologies Pvt Ltd,Bangalore Designing the Server/ Cloud server of required attributes and identifying / trialling software and modalities for hosting content. Rs 9,00,000 30-04-2014 31-01-2017 In progress
21 M/s MRCC Procurement of Server/ Cloud server with required performance, control, the flexibility to scale to in future. Rs 23,55,000 19-06-2015 19-06-2018 In progress
22 M/s MDRA Periodic Road User Satisfaction Survey-I Rs 42,88,107 02-07-2013 04-02-2014 The Proceedings & dissemination posters to be approved by GoK
23 M/s MDRA Periodic Road User Satisfaction Survey-II Rs 42,92,601 14-01-2015 30-06-2016 The Proceedings & dissemination posters to be approved by GoK
24 Mr. Shiva Kumar Menasinakai Mass Communication Expert Rs 11,40,000 02-07-2015 06-01-2016 Completed
Mr. T.S Ranganna Mass Communication Expert Rs 11,40,000 02-11-2016 01-11-2018 In Progress
25 M/s Deccan consultants of Engineering Pvt,ltd,Delhi Independent Environmental monitoring (Pollution Control) for EPC roads & Annuity roads Rs 76,87,829 25-11-2011 31-12-2018 In the 81st meeting of PSC approval given for extension up to Dec 2018. Proposal will be sent to WB For concurrence.
26 M/s HIMS Ltd, New Zeland Consultancy services for Collection of Non-CRN Road condition data for Population and operationalisation of Road information system and pavement management system. Rs 19,37,86,692 25-11-2014 25-11-2016 In Progress
27 M/s Urs Scot Wilson Bangalore Safe Corridor Program-Entrusting preparation of DPR of SCDP Rs 45,00,000 17-10-2014 17-07-2015 Completed
28 M/s Pricewaterhouse coopers Ltd., New Delhi Transaction Advisory services for procurement of 4 Annuity Contract Packages Rs 45,30,000 16-09-2011 16-09-2015 Completed



List of Asian Development Bank Consultancies working for KSHIP-II

Sl No Supervision Consultant Description Contract Value (in INR) Start Date End Date Status
1 M/s SMEC Internationals Ptv Ltd Construction Supervision Consultants for the supervision construction and Contract Administration of ADB Packages Rs 42,10,49,366 12-06-2012 31-9-2017 In Progress
2 M/s.EGIS International S.A.in JV with M/s. EGIS India Consulting Engineers Pvt.Ltd Consultancy Services to Support the Establishment and operation of the Planning and Road Asset Management Centre(PRAMC) for PWD Rs 28,42,60,773 12-02-2013 30-06-2018 In Progress
3 M/s SSRDO NGO services for implementation of Resettlement Acion Plan for North Karnataka Packages Rs 41,13,375 09-05-2011 31-03-2015 Completed
4 M/s SCODWES NGO services for implementation of Resettlement Acion Plan for South Karnataka Packages Rs 51,19,905 09-05-2011 31-03-2015 Completed
5 M/s CMSR M&E Consultants for implementation of Resettlement Action Plan for both packages Rs 39,03,750 11-05-2011 31-05-2015 Completed
6 M/s Sneha Test House Consultancy services for Environmental Monitoring (Pollution) for ADB assisted project roads under KSHIP-II Rs 58,81,200 30-11-2012 30-06-2018 In the 81st PSC approval given for extension up to 30-06-2018. Proposal will be sent to WB for concurrence.
KSHIP road map
WAEP4 AEP3A AEP3B AEP9C AEP9B AEP9A AEP6B AEP6A WAEP3B WAEP3A Note: Mouse over on the map to see the Package Details



WAP-1 : Malavalli to Pavagada
Road Length: 194.34 Km ; Duration: 30 Months Construction + 90 Months Maintenance
Construction Cost: Rs 576 Crores ; Annuity Cost(Biannual): Rs 1306 Cr(239 Cr + 15 Installments of Rs 71.15 Cr)
Construction Schedule: 06-Nov-2014 to 06-May-2017
Executing Agency: M/S Mysore Bellary Pvt Ltd(M/S Sadbhav-GKC(JV))
Construction Supervision Consultant: M/S LEA Associates South Asia Private Ltd
WAP-2 : Mudhol to Nippani
Road Length: 107.94 Km ;   Duration: 24 Months Construction + 96 Months Maintenance
Construction Cost: Rs 331 Crores ; Annuity Cost(Biannual): Rs 768 Cr(136 Cr + 16 Installments of Rs 39.49 Cr)
Construction Schedule: 19-Jan-2015 to 19-Jan-2017
Executing Agency: M/S Ashok Buildcon-GVR(JV)
Construction Supervision Consultant: M/S Aarvee Associates Architects Engineers& Consultants Pvt Ltd
WAEP-3A : Shimoga-Shikaripura-Anandapuram
Road Length: 82 Km ;   Duration: 32 Months
Construction Cost: Rs 264.73 Crores ; Construction Schedule: 28-4-2015 to 27-12-2017
Executing Agency: M/S Patel Engineering Pvt Ltd
Construction Supervision Consultant: M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd
WAEP-3B : Shikaripura-Anavatti-Hangal
Road Length: 71.63 Km ;   Duration: 29 Months Construction
Construction Cost: Rs 224.7 Crores ; Construction Schedule:
Executing Agency: M/S RNS Infrastructure Ltd
Construction Supervision Consultant: M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd
WAEP-4 : Managuli-Devapura
Road Length: 109.953 Km ;   Duration: 33 Months Construction
Construction Cost: Rs 317.05 Crores ; Construction Schedule:
Executing Agency: M/S Sadbhav Engineering Ltd
Construction Supervision Consultant: M/S Roughton International ltd in association with M/S SATRA Infrastructure Management Services Ltd.
WEP1 : Hoskote to Chintamani Bypass of SH-82
Road Length: 52.4 Km ;   Duration: 30 Months
Contract Amount: Rs 98.22 Crores
Schedule: 13-Aug-2011 to 12-Feb-2014
Executing Agency: M/s Lanco Infratech Ltd
Construction Supervision Consultant: EGIS International
WEP2a : Haveri to Hanagal SH-2
Road Length: 31.784 Km ;   Duration: 21 Months
Contract Amount: Rs 92.54 Crores
Schedule: 02-Mar-2013 to 22-Dec-2014
Executing Agency: M/s DRN Infrastructure, Hubli
Construction Supervision Consultant: EGIS International
WEP2b : Hanagal to Tadasa of SH-1, SH-2
Road Length: 43.476 Km ;   Duration: 21 Months
Contract Amount: Rs 97.87 Crores
Schedule:
Executing Agency: M/S DRN Infrastructure
Construction Supervision Consultant: EGIS International
WEP3 : Dharwad to Saundatti of SH-34
Road Length: 36 Km ;   Duration: 41 Months
Contract Amount: Rs 84.44 Crores
Schedule: 28-Jul-2011 to 01-Dec-2014
Executing Agency: M/s RVCPL-RIDL JV
Construction Supervision Consultant: EGIS International
WEP4 : Tinthni to Kalmala of SH-61 & SH-15
Road Length: 73.80 Km ;   Duration: 36 Months
Contract Amount: Rs 160.79 Crores
Schedule: 13-Aug-2011 to 12-Aug-2014
Executing Agency: M/s Patel Engineering Ltd
Construction Supervision Consultant: EGIS International
WEP5 : Chowdapur to Gulbarga of SH-22
Road Length: 28.63 Km ;   Duration: 21 Months
Contract Amount: Rs 61.55 Crores
Schedule: 19-Jul-2011 to 18-Apr-2013
Executing Agency: M/s SRK-KCL JV
Construction Supervision Consultant: EGIS International
AEP1 : Magadi to NH-48 to Koratagere in Tumkur and Ramanagara Districts
Road Length: 68.20 Km ;   Duration: 33 Months
Contract Amount: Rs 116.69 Crores
Schedule: 21-Mar-2012 to 20-Dec-2014
Executing Agency: M/s. KNR Constructions Ltd
Construction Supervision Consultant: SMEC International
AEP2 : Pavagada to AP Border of SH-3
Road Length: 23.205 Km ;   Duration: 18 Months
Contract Amount: Rs 43.30 Crores
Schedule: 29-Mar-2012 to 28-Sep-2013
Executing Agency: M/s. GVR-RMN (JV)
Construction Supervision Consultant: SMEC International
AEP3 : Gubbi to Mandya of SH-84
Road Length: 108.62 Km ;   Duration: 33 Months
Contract Amount: Rs 196.81 Crores
Schedule: 21-Mar-2012 to 06-Dec-2014
Executing Agency: M/s. KMC-VDB (JV)
Construction Supervision Consultant: SMEC International
AEP3A : Gubbi-Beeragonahalli (near Yediyur) of SH-84
Road Length: 49.03 Km ;   Duration: 21 Months
Contract Amount: Rs 122.38 Crores
Schedule:
Executing Agency: M/S DRN Infrastructure, Hubli-30
Construction Supervision Consultant: SMEC International
AEP3B : Beeragonahalli (near Yediyur) - Mandya of SH-84
Road Length: 59.09 Km ;   Duration: 33 Months
Contract Amount: Rs 198.27 Crores
Schedule:
Executing Agency: M/S D.P Jain & Co Infrastructure Pvt Ltd
Construction Supervision Consultant: SMEC International
AEP4 : Jaglur to NH-13 and from SH-19 of KSHIP Road to Molakalmuru of SH-2
Road Length: 14.38 Km ;   Duration: 15 Months
Contract Amount: Rs 31.26 Crores
Schedule: 21-Mar-2012 to 21-Jun-2013
Executing Agency: M/s. GVR-RMN (JV)
Construction Supervision Consultant: SMEC International
AEP5 : Padubidri to Karkala of SH-1
Road Length: 27.80 Km ;   Duration: 18 Months
Contract Amount: Rs 61.27 Crores
Schedule: 05-Mar-2012 to 20-Sep-2013
Executing Agency: M/s. RNS Infrastructure Ltd
Construction Supervision Consultant: SMEC International
AEP6 : Davangere to Birur of SH-76
Road Length: 105.63 Km ;   Duration: 33 Months
Contract Amount: Rs 202.57 Crores
Schedule: 21-Mar-2012 to 20-Dec-2014
Executing Agency: M/s.Gammon India Ltd
Construction Supervision Consultant: SMEC International
AEP6A : Davangere to Channagiri of SH-76
Road Length: 53.65 Km ;   Duration: 21 Months
Contract Amount: Rs 181.45 Crores
Schedule: 15-Dec-2015 to 15-Sep-2017
Executing Agency: M/S JMC Projects (India) Ltd.
Construction Supervision Consultant: SMEC International
AEP6B : Chennagiri to Birur of SH-76
Road Length: 51.98 Km ;   Duration: 22 Months
Contract Amount: Rs 136.78 Crores
Schedule: 1-Sep-2015 to 1-Jul-2017
Executing Agency: M/s D P Jain & Co, Infrastructure Pvt. Ltd.,
Construction Supervision Consultant: SMEC International
AEP7 : Shelvadi to Mundargi of SH-45
Road Length: 63.44 Km ;   Duration: 33 Months
Contract Amount: Rs 121.25 Crores
Schedule: 21-Mar-2012 to 20-Dec-2014
Executing Agency: M/s. KNR Constructions Limited
Construction Supervision Consultant: SMEC International
AEP8 : Mudgal to Gangawathi of SH-29
Road Length: 74.20 Km ;   Duration: 36 Months
Contract Amount: Rs 152.63 Crores
Schedule: 26-Mar-2012 to 25-Mar-2015
Executing Agency: M/s. KNR Constructions Ltd
Construction Supervision Consultant: SMEC International
AEP9 : Soundatti to Kamatagi(including Mulur Ghat) of SH-34 and SH-14
Road Length: 130.13 Km ;   Duration: 36 Months
Contract Amount: Rs 225.50 Crores
Schedule: 21-Mar-2012 to 20-Mar-2015
Executing Agency: M/s. Ramky Infrastructures Ltd
Construction Supervision Consultant: SMEC International
AEP9A : Saundatti to Halagatti Junction(Ramdurga) (including Mullur ghat)
Road Length: 42.065 Km ;   Duration: 21 Months
Contract Amount: Rs 138.24 Crores
Schedule:
Executing Agency: M/S DP Jain & Co Infrastructure Pvt Ltd
Construction Supervision Consultant: SMEC International
AEP9B : Halagatti Junction(Ramdurga) to Badami(including Badami Bypass)
Road Length: 45 Km ;   Duration: 21 Months
Contract Amount: Rs 146.04 Crores
Schedule:
Executing Agency: M/S RNS Infrastructure Ltd
Construction Supervision Consultant: SMEC International
AEP9C : Badami Bypass junction - Pattadakallu - Kamatagi
Road Length: 43.13 Km ;   Duration: 21 Months
Contract Amount: Rs 110.89 Crores
Schedule:
Executing Agency: M/S Ashoka Buildcon Ltd
Construction Supervision Consultant: SMEC International